|
The
following presents a transition plan for implementation of the Framework
until the longer-term implementation plan can be developed and ratified.
The plan draws on discussions with DTI, the presentation and
discussion of organizational options at the November 2, 2000 PSC meeting
and the revisions to the Second Annual Work Plan endorsed by the PSC at
that meeting.
The
SAITIS Project Implementation Plan contemplated that project resources
would be utilized to support the implementation of the ICT Sector
Development Framework. WBS
Activity 2.2.3: Support Implementation of the Strategy (the Strategy is
now referred to as the Framework) included two Work Packages dealing
respectively with Supporting the Creation of a New SAITIS Implementation
Entity and Monitoring and Adjusting the Strategy and its Implementation.
As noted in the introduction, the Project Steering Committee has
endorsed changes to the Second Annual Work Plan that extend the mandate of
the project to permit the SAITIS Project to directly support
implementation activities throughout its remaining life. This will take
the form of the Project Office taking on responsibility to support
implementation, with advisory assistance from the Project Advisors, until
the completion of the project. It should be emphasized that primary
responsibility to undertake implementation rests with DTI, with the
Project Office and the Project Advisors, to the extent that the project
budget permits, supporting DTI.
Transitional
Governance
A
strong governance role is critical in the early implementation of the
Framework. Based on the above analysis, DTI is in the best position to
provide the necessary leadership:
-
DTI
will take the lead in implementing the Framework and will provide the
transitional governance role. This includes responsibility for
providing overall direction for implementation, monitoring progress
and taking corrective action as necessary. It will be necessary for
DTI to establish and support a Program Management role within DTI for
this purpose.
-
DTI’s
role includes responsibility to take the Framework forward for Cabinet
approval and should also include the formation of interdepartmental
consultative mechanisms to co-ordinate the implementation activities
of various departments and agencies. This should also extend to the
engagement of provincial governments in various aspects of
implementation.
-
DTI
should also establish stakeholder engagement mechanisms to seek
advice, commitment and resources in the implementation of the
Framework. In particular, DTI should establish an advisory body such
as that recommended by the PSC to ensure the continued involvement of
the stakeholder groups that contributed to the development of the
Framework.
Since
DTI is not currently staffed to undertake the implementation role, the
Project Office will take on transitional implementation responsibility,
potentially to the end of the project in January 2002. In this activity
the role of the Project Advisors will be to provide advice to the Project
Office on an as needed basis.
As
indicated above, the PSC ratified changes to the Second Annual Work Plan
at its November 2, 2000 meeting that permit the Project to provide this
support. These changes are primarily to WBS 4: Implementation of Plans and
are to retire existing WBS Tasks 4.1 and 4.2 and add three new Tasks as
follows:
4.3
Develop Implementation Plans for the Nine Key Initiatives
4.4
Develop Implementation Plans for the Remaining Fourteen Identified
Initiatives
4.5
Identify New Initiatives and Develop Implementation Plans
Tasks
4.3 and 4.4 are focussed on supporting implementation of the initiatives
in the Going Forward Plan. Task 4.5 will develop new initiatives that
further support the development of the ICT Sector within the context of
the ICT Sector Development Framework. Task 4.5 will also provide the
structure for the development of a comprehensive implementation plan that
addresses the long-term growth and sustainability of the ICT Sector.
The
SAITIS Project Implementation Plan incorporated a management approach that
has allowed for the continued increase in management authority and
responsibilities by South African residents of the Project Office and its
functions. As the project has progressed, greater control has been handed
over to the Project Office in South Africa.
This has been undertaken in a manner that will allow for the
continued operation of the Project Office (or an equivalent operating
agency) as the sustainable entity after the SAITIS Project is complete.
This is in line with the Project Office taking on the transitional
implementation role referred to above. It should be recognized, however,
that the CEA needs to maintain its accountability for the project, and
hence it is not envisaged that total authority will be delegated to the
Project Office during the lifetime of this project.
In
providing support for implementation, the current project organizational
structure and contractual arrangements will be retained. This means that
the Project Director will have management responsibility for the
implementation support activities undertaken by the SAITIS Project. The
Project Director will continue to report to the Project Co-ordinating
Manager, but will maintain a close working relationship with DTI i.e. the
Project Director will be responsive to the transitional governance
approach outlined above. The staff of the Project Office, including the
Project Director, will be assigned responsibility for various of the
initiatives and activities in Tasks 4.3, 4.4 and 4.5. In addition, DTI
earlier indicated a willingness to supplement the staff capabilities of
the Project Office by assignment of two or more people to assist with
implementation support. The cost of providing these people would be
included in DTI’s contribution to the SAITIS Project. If not
forthcoming, the ability of the Project Office to support implementation
will be reduced relative to that anticipated. Financial management of
implementation support will continue as outlined in the Project
Implementation Plan. This
includes the management of any additional funds for implementation that
may be provided by external parties.
The
roles and responsibilities of the Project Advisors during the strategy
development phase have related largely to leading and facilitating the
Project Office staff and other South Africans in strategy development.
Consistent with the Project Office taking on an increased
management role and transitional responsibility for implementation, the
Project Advisors will take on new roles and responsibilities, more
advisory and mentoring, that are suited to the latter stages of the
project. As requested by DTI, and taking into account CIDA’s rules and
regulations regarding assigning new personnel to the project,
PricewaterhouseCoopers will make available its most experienced and
capable people to assist with the planning and implementation of the
initiatives to be supported under WBS Tasks 4.3, 4.4 and 4.5.
Notwithstanding
the shift in emphasis to provide support for implementation, the SAITIS
Project Team must complete the remaining WBS Work Packages as laid out in
the Project Implementation Plan and as modified or will be modified in
Annual Work Plans. Thus the Project Office staff and the Project Advisors
retain responsibility as previously defined to complete this work.
The status at September 30, 2000 and the projected status at the end
of the Second Annual Work Plan of each Work Package are provided in the
Semi-Annual Progress Report, September 2000. The Third Annual Work Plan
will provide details of work activities for the final year of the project. |